Harbours Vale de Cavaleiros and Furna, Cape Verde



Construction of a breakwater covered with 12 t Core-Loc units designed for a 7.2 m high deep water wave, reconstruction and extension of a precast concrete block wall with up to 22 t single wall elements, construction of roll-on / roll-off ramps, construction of a parapet wall and a foreshore protection wall built of concrete elements, capital dredging until –5.5 m, paving and road works.


>> Back
Published on website 01.10.96 - Last update 30.6.08 14:00:05