10.12.2008
Coal-fired power plant of E.ON in Maasvlakte - Rotterdam, Contract: DYWIDAG Bau GmbH, Munich
-
The civil engineering unit of DYWIDAG Bau GmbH, Munich, has today been awarded the contract for the construction of the Maasvlakte Power Plant, Lot 20a, as partner of a joint venture with Ed. Züblin AG, BA Industriebau Duisburg and TBI Bouw B.V., Apeldoorn, The Netherlands. The contract value for the new construction of the power plant (1,100 MW) is 157.936 million euro and covers earthworks, masonry and concrete work for the power station block and the auxiliary facilities. The construction period will be almost 3 years.
|
|
|
|
|
|
|
|
|
|